Project Details
ASU Recreation/Wellness Center and Center for Human Performance Expansion
| Project #: | 08-26 |
| Detailed Status: | Project Closed |
| Building Gross Sq. Ft: | 102,953 |
| Campus: | ASU San Angelo |
| Budget | |
| Board Approved Budget: | $7,000,000 |
| Adjusted Budget: | $7,000,000 |
| Final Cost: | $6,938,280 |
| Schedule | |
| Construction Start Date: | 03.21.2010 |
| Project Completion: | 04.01.2011 |
| Project Team | |
| Program Director: | John Russell |
| Contractor: | Lee Lewis Construction, Inc. |
| Design Professionals: | Smith Group/F&S |
| CM Agent: | N/A |
| Description | |