Project Details
BSL-3 Lab at the Institute for Environmental Human Health
| Project #: | 11-19 | 
| Detailed Status: | Project Closed | 
| Building Gross Sq. Ft: | 44,284 | 
| Campus: | TTU Lubbock | 
| Budget | |
| Board Approved Budget: | $2,400,000 | 
| Adjusted Budget: | $2,400,000 | 
| Final Cost: | $2,030,475 | 
| Schedule | |
| Construction Start Date: | 09.24.2012 | 
| Project Completion: | 04.26.2013 | 
| Project Team | |
| Program Director: | Bill Droll | 
| Contractor: | AUI Contractors | 
| Design Professionals: | Perkins + Will | 
| CM Agent: | N/A | 
| Description | |
| Biological Safety Level 3 to be designed and constructed at the Reese Technology Center. | |