ASU Carr Hall Renovation
Project #: | 22-03 |
Detailed Status: | Warranty |
Building Gross Sq. Ft: | 20,920 |
Campus: | ASU San Angelo |
|
Board Approved Budget: | $8,561,645 |
Adjusted Budget: | $8,561,645 |
|
Construction Start Date: | 05.30.2023 |
Project Completion: | 03.11.2024 |
|
Program Director: | Jeff Sutherland |
Contractor: | Hoar Construction |
Design Professionals: | O'Connell Robertson |
CM Agent: | N/A |
Artist: | N/A |
Art Title: | N/A |
|
Complete interior renovation of Carr Hall, which is an 20,920 GSF, two-story structure built in 1959. The project will modernize the campus residential facility with an anticipated 64-bed count. |