Project Details
Jones AT&T Stadium North End Zone Expansion
| Project #: | 09-05 |
| Detailed Status: | Project Closed |
| Campus: | TTU Lubbock |
| Location: | 6 Red Raider Avenue |
| Budget | |
| Board Approved Budget: | $6,000,000 |
| Adjusted Budget: | $6,000,000 |
| Final Cost: | $5,998,165 |
| Schedule | |
| Construction Start Date: | 05.18.2009 |
| Project Completion: | 01.01.2011 |
| Project Team | |
| Program Director: | Debbie Cox |
| Contractor: | Lee Lewis Construction |
| Design Professionals: | Heery International; MWM Architects, Inc. |
| CM Agent: | N/A |
| Description | |
| This project added 6,182 seats to the North End Zone. Accessible seating was added to the top of the existing bowl. The Ticket Office Building remains. | |