Project Details
Video Scoreboard Package
| Project #: | 12-12 |
| Detailed Status: | Project Closed |
| Building Gross Sq. Ft: | 3,420 |
| Campus: | TTU Lubbock |
| Budget | |
| Board Approved Budget: | $11,000,000 |
| Adjusted Budget: | $11,000,000 |
| Schedule | |
| Construction Start Date: | 12.04.2012 |
| Project Completion: | 09.06.2013 |
| Project Team | |
| Program Director: | Ross John Narvaeth |
| Contractor: | Vaughn Construction |
| Design Professionals: | MWM Architects, Inc.; Rogers Moore Engineer; Anthony James Partners, LLC |
| CM Agent: | N/A |
| Description | |
| This project constructs a super-structure that spans over the Athletic Ticket Office building at the Jones AT&T Stadium north end zone. The structure supports a state-of-the-art, high-definition video screen and surrounding sponsor screens and graphics. The project also includes video display panels (ribbon boards) and a new sound system that uses the latest digital audio technology. | |