Project Details
Jones AT&T Stadium Renovation - SE 1st Floor
| Project #: | 14-15 |
| Detailed Status: | Project Closed |
| Building Gross Sq. Ft: | 6,619 |
| Campus: | TTU Lubbock |
| Budget | |
| Board Approved Budget: | $1,650,000 |
| Adjusted Budget: | $1,650,000 |
| Final Cost: | $1,323,461 |
| Schedule | |
| Construction Start Date: | 03.27.2015 |
| Project Completion: | 07.25.2015 |
| Project Team | |
| Program Director: | Steve Forman |
| Contractor: | Teinert Commercial Building Services |
| Design Professionals: | MWM Architects |
| CM Agent: | N/A |