Project Details
Jones Stadium - NE Corner Renovation
| Project #: | 15-02 |
| Detailed Status: | Project Closed |
| Building Gross Sq. Ft: | 4,635 |
| Campus: | TTU Lubbock |
| Budget | |
| Board Approved Budget: | $868,066 |
| Adjusted Budget: | $868,066 |
| Final Cost: | $782,935 |
| Schedule | |
| Construction Start Date: | 01.07.2016 |
| Project Completion: | 03.09.2016 |
| Project Team | |
| Program Director: | Steve Forman |
| Contractor: | Teinert Commercial Building Contractors. |
| Design Professionals: | MWM Architects, Inc. |
| CM Agent: | N/A |