Project Details
TTUHSC - Dallas Southwest Professional Building Renovation-Sixth Floor
| Project #: | 19-17A | 
| Detailed Status: | Project Closed | 
| Building Gross Sq. Ft: | 18,440 | 
| Campus: | HSC Dallas | 
| Location: | 5920 Forest Park Road | 
| Budget | |
| Board Approved Budget: | $6,781,070 | 
| Adjusted Budget: | $6,781,070 | 
| Final Cost: | $5,371,844 | 
| Schedule | |
| Construction Start Date: | 08.01.2022 | 
| Project Completion: | 07.14.2023 | 
| Project Team | |
| Program Director: | Todd Hardin | 
| Contractor: | Hill & Wilkinson | 
| Design Professionals: | Page | 
| CM Agent: | N/A | 
| Artist: | N/A | 
| Art Title: | N/A |